Climate Change Resilience Project: Phase 8 – Sincere Thanks   Our Climate Change Resilience Project is substantially completed for this year. Hydro seeding and hand seeding are the last remaining touches

Share

Climate Change Resiliency Project Phase 7: Final Touches Our Climate Change Resiliency Project is now into its final stages, and we are thrilled with the results. Last week’s post highlighted,

Share

Climate Change Resiliency Project: Phase 6 Dozer-time.   Our Climate Change Resiliency Project is nearing completion. With the lower mountain bisect road completed and most of the base area infill delivered,

Share

Climate Change Resiliency Project: Phase 5 Building the road Our Climate Change Resiliency Project is moving along very well. At the end of this week, the lower mountain bisect road

Share

Our Climate Change Resiliency Project Had a highly successful week. The material generating blast took place, and we are pleased with the abundant results. Heavy equipment in the form of dozers, excavators,

Share

2024 MMC-Shames Mountain – Town Hall Summary Firstly, thank you to everyone who joined the 2024 Virtual Town Hall. Your continued support is invaluable.  We recorded the Town Hall –

Share

Climate Change Resiliency Project: Phase 4 – Blasting, Sorting and Placing Materials Our Climate Change Resiliency Project is making great strides and we are due to enter an exciting new

Share

Changes for 2024-2025: Age categories will shift slightly as of July 1st 2024. This will allow MMC-Shames Mountain to be the first ski hill in Canada to offer unlimited FREE

Share

Following recommendations from the Pricing Committee, the Board accepted the new price increases for the 2024-2025 winter season. The ski hill’s expenses are increasing. Increases to minimum wage, insurance costs

Share

This coming week at the mountain, starting June 17th, we are waiting on confirmation of when our blasting day will commence. As we we patiently wait for a date to

Share