Our Climate Change Resiliency Project Had a highly successful week. The material generating blast took place, and we are pleased with the abundant results. Heavy equipment in the form of dozers, excavators,
2024 MMC-Shames Mountain – Town Hall Summary Firstly, thank you to everyone who joined the 2024 Virtual Town Hall. Your continued support is invaluable. We recorded the Town Hall –
Climate Change Resiliency Project: Phase 4 – Blasting, Sorting and Placing Materials Our Climate Change Resiliency Project is making great strides and we are due to enter an exciting new
Changes for 2024-2025: Age categories will shift slightly as of July 1st 2024. This will allow MMC-Shames Mountain to be the first ski hill in Canada to offer unlimited FREE
Following recommendations from the Pricing Committee, the Board accepted the new price increases for the 2024-2025 winter season. The ski hill’s expenses are increasing. Increases to minimum wage, insurance costs
This coming week at the mountain, starting June 17th, we are waiting on confirmation of when our blasting day will commence. As we we patiently wait for a date to
Monday, June 10th 2024, will see infill material hauled from the Delta Creek landslide site to the base area of MMC-Shames Mountain. On Tuesday, June 11th, 2024 we will be
Our Climate Change Resiliency Project is entering a drilling and blasting phase. We will be generating a portion of the infill materials needed for the base area and the lower
Our Climate Change Resiliency Project has commenced. Please respect the closures as our team start work in the lower mountain. Until further notice there is no access from the base