Climate Change Resilience Project: Phase 8 – Sincere Thanks Our Climate Change Resilience Project is substantially completed for this year. Hydro seeding and hand seeding are the last remaining touches
Climate Change Resiliency Project Phase 7: Final Touches Our Climate Change Resiliency Project is now into its final stages, and we are thrilled with the results. Last week’s post highlighted,
Climate Change Resiliency Project: Phase 6 Dozer-time. Our Climate Change Resiliency Project is nearing completion. With the lower mountain bisect road completed and most of the base area infill delivered,
Climate Change Resiliency Project: Phase 5 Building the road Our Climate Change Resiliency Project is moving along very well. At the end of this week, the lower mountain bisect road
Our Climate Change Resiliency Project Had a highly successful week. The material generating blast took place, and we are pleased with the abundant results. Heavy equipment in the form of dozers, excavators,
Climate Change Resiliency Project: Phase 4 – Blasting, Sorting and Placing Materials Our Climate Change Resiliency Project is making great strides and we are due to enter an exciting new
This coming week at the mountain, starting June 17th, we are waiting on confirmation of when our blasting day will commence. As we we patiently wait for a date to
Monday, June 10th 2024, will see infill material hauled from the Delta Creek landslide site to the base area of MMC-Shames Mountain. On Tuesday, June 11th, 2024 we will be
Our Climate Change Resiliency Project is entering a drilling and blasting phase. We will be generating a portion of the infill materials needed for the base area and the lower